[Rubycocoa-devel 729] 1.0 milestone

Back to archive index

Laurent Sansonetti lsans****@apple*****
Sat Feb 10 13:02:18 JST 2007


Hi all,

Let's discuss the 1.0 milestone plan.  Hisa-san and I suggest to  
release RubyCocoa 1.0 the 16th April.

To reach this milestone, here is the plan:

- merge the bundle support branch to apple unstable
- merge the IB tool to apple unstable
- finish the documentation support

Then,

- copy apple unstable to trunk
- trunk becomes the development area (adding new features, etc...)
- apple unstable will only be bug fixes, no new feature - all changes  
will have to be introduced very carefully

And finally we will use apple unstable for RubyCocoa 1.0.

We have a bit more than 2 months so!

Any thoughts?

Laurent